A single federal award, with both ends of the trail linked.

$47M
Total award value

Award 693JJ22640031Y180NJB260031BIPS is a grant from the Department of Transportation, $47M obligated, FY2026 to FY2032, for Replacement of Lincoln Avenue Bridge Over Amtrak and Assunpink Creek. The work is performed in New Jersey. Source

Description

Project Title: Replacement of Lincoln Avenue Bridge Over Amtrak and Assunpink Creek :::: Project Description: This Mercer County Bridge Carries Lincoln Avenue (County Route 626) Over Amtrak’s Northeast Corridor Rail Line, an Abandoned Rail Yard, and Assunpink Creek. This Grant Request Is to Provide Gap Funding for a Full Replacement of This Deficient Structure. The Bridge Is a Critical Multimodal Facility Within the Economically Disadvantaged City of Trenton. With Blocks of Concrete Spalling Off the Structure Over the Train Tracks, a Replacement Project Is Entering Final Design. Federal Funds Replacement of Four Other Structurally Deficient Bridges Over Amtrak in Mercer County Are in Early Stages of Development (Three State, One County, None Yet Programmed). The Lincoln Avenue Bridge Is Furthest Along. Without a Grant Award, IT Will Be Challenging for the Region and State to Advance the Lincoln Avenue Bridge Project to Construction.

Award details

Award typeGrant
FAIN693JJ22640031Y180NJB260031BIPS
Action date2026
Period68 mo
RecipientOutside our Phase 1 contractor set: see methodology
Place of performanceNew Jersey →
Category—
Competed?Not recordedSource
Total (exact)$47,000,000

More from Department of Transportation

awarded 2022$15.6B
awarded 2022$6.2B
awarded 2022$5.9B
awarded 2021$4.1B
Why the labels? The graph is only worth anything if the links are trusted. Facts taken straight from a federal filing are Source; figures we calculate are Computed; links we infer (corporate parents, districts, similar contractors, connections between records) are Inferred, worded carefully, never asserted as fact and never a claim that one thing caused another. Spot an error? Tell us.