Construct Taxiway. Activities to Be Performed/Expected Outcomes: This Project Constructs New 4,200 Foot…
FY2026 ended Sep 30 · data still posting · data as of 2026-11-01†
† DoD contract data posts to USAspending about 90 days after award.
A single federal award, with both ends of the trail linked.
Award 34900331522026 is a grant from the Department of Transportation, $17M obligated, FY2026 to FY2030, for Construct Taxiway. Activities to Be Performed/Expected Outcomes: This Project Constructs New 4,200…. The work is performed in Utah. Source
Description
Purpose: Construct Taxiway. Activities to Be Performed/Expected Outcomes: This Project Constructs New 4,200 Foot Taxiway U to Bring the Airport Into Conformity with Current Standards. This Grant Funds Phase 4, Which Consists of Construction of the Taxiway Bridge. . Intended Beneficiary: This Grant Will Provide Federal Funding for Airports Associated with Salt Lake City, Utah.