Construct/Extend Safety Area
FY2026 ended Sep 30 · data still posting · data as of 2026-11-01†
† DoD contract data posts to USAspending about 90 days after award.
A single federal award, with both ends of the trail linked.
Award 33400230722026 is a grant from the Department of Transportation, $14.2M obligated, FY2026 to FY2030, for Construct/Extend Safety Area. The work is performed in New Jersey. Source
Description
Purpose: Construct/Extend Safety Area. Activities to Be Performed/Expected Outcomes: This Project Constructs Runway 5/23 Safety Area at Both Runway Ends to Enhance Safety. This Grant Funds Phase 12, Which Consists of Grading Work in the Runway Safety Area. NON-14 CFR Part 139 Certificated Airports Were Not Subject to the Runway Safety Area Deadline of December 31, 2015, and Some Airports, Including This One, Continue to Pursue Further Improvements as They Become Feasible. Intended Beneficiary: This Grant Will Provide Federal Funding for Airports Associated with Morristown, New Jersey.