Award Purpose This Project Will Fund the Following Elements Strengthen Nine Acres of Pavement for Flexible…
FY2024 · complete year · data as of 2026-07-03
A single federal award, with both ends of the trail linked.
Award 693JF72344022 is a grant from the Department of Transportation, $24.4M obligated, FY2024 to FY2028, for Award Purpose This Project Will Fund the Following Elements Strengthen Nine Acres of Pavement for…. The work is performed in Oregon. Source
Description
Award Purpose This Project Will Fund the Following Elements Strengthen Nine Acres of Pavement for Flexible Cargo Storage Including Container Storage Upgrade Pavement Throughout 30 Acres of Cargo Storage Yard Add a Stormwater Treatment System to Reduce Pollutants Entering the Columbia River Replace Electrical Components to Reduce Energy Consumption Light Spillage and Enable Future Zero Emission Operations and Install Two Emergency Generators to Provide Backup Power During Seismic Events or Other Power Outages. Activities to Be Performed the Project Consists of Improvements to Pavement Electrical Systems and Stormwater Systems to Increase the Energy Efficiency Productivity and Safety of All Types of Cargo Handling at Marine Terminal 6 T6 Including Strengthening Roughly Nine Acres of Pavement for Flexible Container and Cargo Storage Including Break Bulk Products Such as Utility Generators Heavy Duty Batteries Steel Slab Wind Energy Components Such as Blades Tower Sections and Nacelles Heavy Duty Vehicles and Parts; Upgrading Pavement Throughout Approximately 30 Acres of Cargo Storage Yard Where Deteriorated Conditions Limit the Ability to Safely Transport Store, and Stack Cargo and Adding a Stormwater Treatment System to Reduce Pollutants Entering the Columbia River. Replacing Electrical Components of the Cargo Storage Yard to Reduce Energy Consumption and Light Spillage Increase Safety and Security Enable Future Zero-Emission Operations and Install Two Emergency Generators to Provide Backup Power During Seismic Events or Other Power Outages. The Project Is Comprised of Four Components Component 1 Project Management and Grant Administration Provide Project Management of Including But Not Limited to Scope Schedule and Budget. Provide Project Support Not Contracted Under Components 2 3 and 4 Below E.g. For Internal Staff Including But Not Limited to Advertise and Bid Each Design and Construction Contract. Perform Construction Inspection Contract Management and Close Out. Provide Survey RFI Review and Material Testing. Obtain Required Local State and Federal Permits. Component 2 Design and Permitting Design Pavement and Stormwater Improvements at Yard 607 Collectively B607 Improvements and Lighting and Electrical Improvements in Yards 604 605 and 606 Collectively Light and Electrical Improvements Through Development of Construction Contract Documents. Support Local State and Federal Permitting Processes. Provide Technical Support During Construction and Construction Contract Close-Out Activities E.g. Responding to Rfis Verifying as Constructed Red Line Drawings Etc. Component 3 B607 Improvements Strengthen Approximately Nine Acres of Pavement in the Yard 607 Area Adjacent to the Auto Terminal to Serve as a Flexible Multiple Cargos Storage Area. Upgrade Pavement in a Limited Number of Targeted Areas Within Approximately 30 Acres of Cargo Storage Yard Selected for Greatest Near Term Operational Benefit Where Deteriorated Conditions Limit the Ability to Safely Transport and Stack Containers and Other Cargo. Construct a New Stormwater Collection System to Reduce Pollutants Entering the Columbia River from the Yard. Replace Lighting System Components in This Area. Component 4 Light and Electrical Improvements Upgrade Electrical Components to Provide the Port with a More Energy Efficient and Resilient Network for the Cargo Storage Yard, Including Install New Electrical Duct Between T6 Utility Structures to Provide a Pathway for Medium Voltage Feeder Upgrade and Future Operations. Replace Substation a Lineup of Fused Air Switches and Medium-Voltage Air Feeders and Switches That Have Exceeded Their Anticipated Service Lives. Install New Conduit and Switches for Future Shore Power and Yard Equipment Charging. Install Generators and Automatic Transfer Switches at the Critical Operational Locations (Administration Building and T6 Entry Exit Gate. Replace 207 High Mast High Pressure Sodium HPS Lighting Fixtures with Led Lighting and a Wireless Control System. Replace Oil-Filled Transformers on Top of Utility Structures with Ground-Level Dry Type Transformers. Deliverables Expected Outcomes Performance Measure Table from Schedule G Page 13 of the Grant Agreement. Intended Beneficiary Port of Portland. Subrecipient Activities None.