Activities to Be Performed: The Activities to Be Performed Are as Follows:-Compliance Nepa-Pipe Order…
Description
Purpose: Activities to Be Performed: The Activities to Be Performed Are as Follows:-Compliance Nepa-Pipe Order Acquisition-Pipe Delivery for Spur and Highline Sites-Highline Site Pipe Installation-Spur Drop Site Pipe Installation-Pipe Delivery for Memorial Site-Spur Drop Pump Station-Jack and Bores Completion-Memorial Site Pipe Installation-Memorial Pump Station-Completion of Phase 1-COMPLETION of Phase 2-FINAL Project Reportexpected Deliverables or Outcomes: The Outcome If This Project Will Be the Laying of Over 19 Miles of New Reclaimed Water Pipe and Creation of New Pumping Stations. Intended Beneficiaries: The United States Public and the Recipient Are the Intended Beneficiaries. Subrecipient Activities: The Recipient Will Contract for the Site Clearing, Installation of Pipe, Installation of Pumping Stations, Excavations, Design Costs, and Pipe Acquisition.